Case Study

COMMERCIAL CONCRETE · LYNCHBURG, VA · NEW BUILD

A $376,426 concrete package, priced in two minutes.

A Virginia concrete contractor uploaded the architect’s plan set for a municipal fire station. Loadbare returned eight scope items with quantities, unit costs, crew hours and dollars. Here is the entire estimate, unedited.

Headline figures

  • $376,426

    Total priced

  • 8

    Scope items

  • 1,739

    Crew hours

  • ~2 min

    To produce

Priced for an 8 person crew at $65 an hour with a 20 percent margin, which are this contractor’s own calibrated rates rather than a national price book. Change the crew rate or the margin and every line re-prices.

The Estimate

EIGHT LINES · FOUR WORK AREAS · EVERY FIGURE DEFENSIBLE

Line by line, the way an owner would check it.

Full line item estimate for the fire station concrete package
Work area Scope item Quantity Unit cost Crew hrs Line total
Building perimeter / interior footing lines Footing excavation and trenching 650 linear ft $3.00 78.0 $7,020
Continuous footings, formed and poured with rebar 650 linear ft $22.00 195.0 $26,975
Interior slab-on-grade area Stone base, compacted (4 to 6 in) 17,048 sqft $1.10 204.6 $32,050
Rebar and mesh reinforcement, slab 17,048 sqft $0.85 136.4 $23,356
Concrete slab foundation 17,048 sqft $7.00 852.4 $174,742
Exterior aprons, sidewalks, pads Stone base, compacted (4 to 6 in) 4,000 sqft $1.10 48.0 $7,520
Exterior concrete flatwork (aprons, walks, pads) 4,000 sqft $5.50 180.0 $33,700
Site entrance curb and gutter Concrete curb and gutter 300 linear ft $18.00 45.0 $8,325
Subtotal, materials, subs and labor1,739.4 hrs$313,688
Overhead and margin, 20 percent$62,738
Quoted total$376,426

The slab alone is 17,048 square feet carrying 852 crew hours. Stone base, rebar and mesh, and the pour are costed separately rather than buried in a single square foot rate, so when an owner pushes back on price you can show exactly which line moves.

How It Ran

PLAN SET IN · ESTIMATE OUT · DRAW SCHEDULE ATTACHED

Three moves, no estimator.

  1. 01 · UPLOAD

    The plan set went in.

    An architect’s PDF, the same file the general contractor sent out for bid. No takeoff software, no measuring wheel, no tracing.

  2. 02 · PRICE

    Eight lines came back.

    Quantities read off the drawings, then costed on this contractor’s own rates. Roughly two minutes from upload to a sendable estimate.

  3. 03 · SEND

    Out for signature.

    Client link with e-signature, deposit collected on signing, and a draw schedule with retainage tracking what is invoiced against what actually landed.

Bring a real bid to a call and we will price it live on your numbers while you watch. If the output is not close enough to send, you have lost twenty minutes.